Water Main Improvement Program - Phase 2B

Construction Progress Update
​Friday, July 25, 2016

General Project Information
​1. Construction began on Monday, April 25, 2016
​2. Contract Day 91 of 150

NORTH AREA UPDATE (Travers Ln, Marston Ln, Cummings Ln, Hutchison Rd, Vardon Ln., Latimer Ln.)

Work Completed to Date:
​1. All work is 100% complete

Restoration Notes:
​1. Many areas where grass was restored will settle after rain events. The contractor is aware of this and will come back to fix all these settled areas in the early fall.

SOUTH AREA UPDATE (Tina Ln, Markey Ln, Thomas Ct., Pinehurst Ln.)

​ 1. Water main work in the south area is scheduled to begin the week of August 1, 2016

​ Please call Public Works at 708-957-4100 if you have any questions or need additional information.

​______________________________________________________________________________________________